TY - JOUR
T1 - Factors influencing Time and Cost Overruns on Freeform Construction Projects
AU - Kavuma, Andrew
AU - Ock, Jongho
AU - Jang, Hyounseung
N1 - Publisher Copyright:
© 2019, Korean Society of Civil Engineers.
PY - 2019/4/1
Y1 - 2019/4/1
N2 - Freeform buildings differ from conventional buildings in a way that they have irregularly shaped facades. Oftentimes, freeform projects run behind schedule and over the budget. This study aimed at exploring factors that influence time and cost overruns on freeform buildings. The study employed questionnaire surveys to collect data from experts with freeform project experience, and the responses were analyzed using R statistical program. The study used exploratory factor analysis to identify the most critical latent factors to freeform project success. The study found factors related to application of Building Information Modeling (BIM) and fabrication of freeform components as very crucial to timely completion, whereas factors related to personnel involved as essential to completing within budget. Additionally, the study summarized time overrun variables into three latent factors; uniqueness, capabilities and practices of the parties involved, and level of preparation for the project. The cost overrun latent factors were: cost uncertainty, client decisions, extent of preparation, and delay. Understanding the causes of time and cost overruns on freeform buildings identified in this study can help clients make informed decisions regarding undertaking freeform projects as well as help consultants and contractors minimize the risk of encountering such overruns.
AB - Freeform buildings differ from conventional buildings in a way that they have irregularly shaped facades. Oftentimes, freeform projects run behind schedule and over the budget. This study aimed at exploring factors that influence time and cost overruns on freeform buildings. The study employed questionnaire surveys to collect data from experts with freeform project experience, and the responses were analyzed using R statistical program. The study used exploratory factor analysis to identify the most critical latent factors to freeform project success. The study found factors related to application of Building Information Modeling (BIM) and fabrication of freeform components as very crucial to timely completion, whereas factors related to personnel involved as essential to completing within budget. Additionally, the study summarized time overrun variables into three latent factors; uniqueness, capabilities and practices of the parties involved, and level of preparation for the project. The cost overrun latent factors were: cost uncertainty, client decisions, extent of preparation, and delay. Understanding the causes of time and cost overruns on freeform buildings identified in this study can help clients make informed decisions regarding undertaking freeform projects as well as help consultants and contractors minimize the risk of encountering such overruns.
KW - Building Information Modeling (BIM)
KW - cost overruns
KW - freeform projects
KW - latent factors
KW - time overruns
UR - https://www.scopus.com/pages/publications/85061992785
U2 - 10.1007/s12205-019-0447-x
DO - 10.1007/s12205-019-0447-x
M3 - Article
AN - SCOPUS:85061992785
SN - 1226-7988
VL - 23
SP - 1442
EP - 1450
JO - KSCE Journal of Civil Engineering
JF - KSCE Journal of Civil Engineering
IS - 4
ER -