N2 - Temporary fabrication plants such as rebar assembly and precast segment shops are increasingly used in large scale construction projects to provide a construction site of its material needs. A plant needs to be operated in such a way that it is flexible enough to adapt to changing project demands while minimizing inventories. Meeting such needs requires careful control of the level of raw materials and assembly products fabricated in the plant, the two main types of inventories. However, in practice the ordering of raw materials and assembly times are ad hoc, leading to excess inventories and added costs to the project. This paper presents a methodology for effective, efficient, and economic control of inventory levels in temporary rebar assembly plants. Ordering processes are formalized to convert existing approaches into a pull production system. Given this transformation, a methodology is presented that employs Monte Carlo simulation and optimization techniques to identify inventory levels that minimize inventory costs while simulating variability in demand, procurement lead times, and production capacity. A retrospective case on a rebar assembly plant shows that the same amount of work can be performed with significantly less inventory levels when applying the proposed production methodology. It also provides evidence that the cost savings from inventory costs outweigh any additional holding or delivery costs associated with a pull production system.
AB - Temporary fabrication plants such as rebar assembly and precast segment shops are increasingly used in large scale construction projects to provide a construction site of its material needs. A plant needs to be operated in such a way that it is flexible enough to adapt to changing project demands while minimizing inventories. Meeting such needs requires careful control of the level of raw materials and assembly products fabricated in the plant, the two main types of inventories. However, in practice the ordering of raw materials and assembly times are ad hoc, leading to excess inventories and added costs to the project. This paper presents a methodology for effective, efficient, and economic control of inventory levels in temporary rebar assembly plants. Ordering processes are formalized to convert existing approaches into a pull production system. Given this transformation, a methodology is presented that employs Monte Carlo simulation and optimization techniques to identify inventory levels that minimize inventory costs while simulating variability in demand, procurement lead times, and production capacity. A retrospective case on a rebar assembly plant shows that the same amount of work can be performed with significantly less inventory levels when applying the proposed production methodology. It also provides evidence that the cost savings from inventory costs outweigh any additional holding or delivery costs associated with a pull production system.
KW - Construction supply chain
KW - Inventory control
KW - Pull production
KW - Temporary fabrication plant
UR - https://www.scopus.com/pages/publications/70350223481
U2 - 10.1139/L09-072
DO - 10.1139/L09-072
M3 - Article
AN - SCOPUS:70350223481
SN - 0315-1468
VL - 36
SP - 1444
EP - 1458
JO - Canadian Journal of Civil Engineering
JF - Canadian Journal of Civil Engineering
IS - 9
ER -